The below information relates to minor works in Hamilton city.

 

Casey Avenue
Entire Length
Ranfurly Gully Project
Wastewater Replacement
August 2025 to mid 2026
Cambridge Road
from Wairere Drive to Masters Avenue
Safety Improvements 5 January to 17 March 2026
Delamare Road Minor Footpath Repair Concrete 9 March to 20 March 2026
Madill Road Minor Footpath Repair Concrete 9 March to 20 March 2026
Dallinger Street Minor Footpath Repair Concrete 9 March to 20 March 2026
2, 27, 39A, 53, 84 Powells Road Minor Footpath Repair Concrete 9 March to 20 March 2026
4 Corrin Street Minor Footpath Repair Asphalt 9 March to 20 March 2026
1, 10, 12, 38 Horne Street Minor Footpath Repair Asphalt 9 March to 20 March 2026
4, 21 Jones Cres Minor Footpath Repair Asphalt 9 March to 20 March 2026
19 Beatty Street Minor Footpath Repair Asphalt 9 March to 20 March 2026
opposite 39 Foreman Road Minor Footpath Repair Asphalt 9 March to 20 March 2026
149 Peachgrove Road Minor Footpath Repair Asphalt 9 March to 20 March 2026
Tasman Road,
(Crn Te Kowhai East)
Minor Footpath Repair Asphalt 9 March to 20 March 2026
Hillcrest Road Minor Footpath Repair Asphalt 16 March to 20 March 2026
Knighton Road
from Cambridge Road to Brocas Avenue
Watermain Replacement 2 July 2025 to 19 March 2026
Collins Road
from Deanwell Avenue to Lilac Street
Wastewater Storage Tank Installation 31 August 2024 to 30 April 2026
Ward Street
from Anglesea Street to Seddon Road
Watermain Replacement 9 August 2025 to 3 May  2026
Bader Street
Montgomery Street
Intersection
Watermain Upgrade 3 November 2025 to 26 April 2026
Norrie Street
Manor Place
Intersection
Wastewater Replacement 11 February  to 26 March 2026