What is chipsealing?

Chipsealing is one of the two main ways we reseal our roads. Much like paint on a house, the seal of a road acts as a protective layer for the structure underneath, keeping water out and providing a safe surface to drive on. Resealing the road is like applying a fresh coat of paint to keep it in good condition.  

The chipsealing process involves applying a layer of bitumen (the sticky stuff that our roads are made of) and covering it with a layer of chip (small stones). Depending on the road's condition and amount of traffic, sometimes two layers of bitumen and chip are applied to create a stronger, long-lasting surface. Once complete, a new seal is expected to last for between 7 - 20 years. 

Chipsealing can be done at any time of day, as long as the weather is dry and the temperature is hot enough. Most sites are typically completed within a few hours. If the weather is unsuitable, work will be rescheduled to the next good weather day in our programme. 

2026/27 Chipsealing season

The below streets are currently planned for chipsealing as part of the 2026/27 construction season. Most sites are programmed to be completed in January and February 2027. Please note this list may be subject to change.

Location Start  End
Albert Street Grey Street Firth Street
Armagh Street End of cul-de-sac only
Bader Street Willis Street Montgomery Crescent
Beale Street Grey Street roundabout Hamilton Boys' High School
Beatty Street Entire street
Church Road Balmerino Crescent The Lookout Bar and Kitchen
Colstone Street Entire street
Cussen Street Entire street
Dawson Street Puutikitiki Street End of cul-de-sac
Dinsdale Road Caernarvon Street Dinsdale roundabout
Douglas Crescent Entire street
East Street Peachgrove Road Wairere Drive underpass
Exeter Street Entire street
Fairfield Road River Road Ranfurly Avenue
Fox Lane Entire street
Fox Street Naylor Street Brookfield Street
Galloway Street Cobham Drive Brookfield Street
Garthwood Road Vista Terrace End of cul-de-sac
Grey Street Dawson Street Te Aroha Street
Hammond Street Palmerston Street Park Terrace
Hendon Road Entire street
Higgins Road Kahikatea Drive End of cul-de-sac
Holmes Street Entire street
Jennifer Place Entire street
Lloyd Drive Baverstock Road Crawshaw Drive
Nevada Road Chelmsford Street End of cul-de-sac
Newall Street Entire street
Norrie Street Loop from Peacockes Road
Ohaupo Road Service Lane Entire street
Paul Crescent Holland Road Fairfield Park entrance
Peachgrove Road Five Cross Roads roundabout Alfred Street
Ruffell Road Arthur Porter Drive End of cul-de-sac
Rumney Street Entire street
Scott Avenue Entire street
St Kilda Place Entire street
Thomas Road Hukanui Road roundabout Cate Road
Totara Drive Sandwich Road Totara Drive Overbridge
Tramway Road  Wairere Drive Insoll Avenue
Wilson Street Peachgrove Road Pinfold Avenue
Wye Street Taniwha Street Torrington Avenue

Frequently asked questions

Why do some roads get chipseal and others get asphalt?

The other main method we use to reseal our roads is asphalt resurfacing. The method we choose is matched to the type of road.

For example, chipseal is a cost-effective solution for local roads that have less traffic, heavy vehicles, or turning movements that can put strain on the road over time, whereas asphalt is used for busy streets and intersections that require a more resilient surface.

To learn more about asphalt and our road maintenance programme, visit our Maintenance and Management page.

How are roads selected for chipsealing each year?

Roads are selected based on factors including the age and condition of the road, traffic volumes and types, and safety risk. We prioritise where resurfacing is most needed.

If there is other planned infrastructure activities programmed to take place in the near future, e.g, water renewals or transport improvements, we may delay chipsealing of a road to a later year to avoid the new seal becoming dug up.

Why is my street being chipsealed if it looks fine?

The most effective time to reseal is before obvious damage like potholes appears in the road surface. We use condition information and inspections to identify early signs of deterioration, so if we’re resealing your road it means we’ve noted issues that need to be addressed, even if they don’t seem obvious.

Is all work completed at the same time?

No, depending on the road surface condition we may need to complete pre-seal repairs before the chipsealing. Once the chipsealing is completed, we return to do sweeping and road marking.

What are pre-seal repairs?

Pre-seal repairs are minor repairs completed before a road is resealed. These are targeted fixes to the road surface, drainage, or kerb and channel, and are usually completed a few months prior to a reseal. Completing these repairs ahead of time addresses defects and prevents water from getting into the road structure – which could reduce the life of the new chipseal.

Why is there loose chip left on the road?

Loose chip is a normal part of the chipsealing process. Enough chip is applied to fully cover the  sticky binder while it sets. As vehicles travel over the road, traffic helps press the chip into the surface and moves loose chip into the gaps. Any excess chip is then swept to keep the road safe and tidy.

When will the loose chip be swept?

A first sweep happens within two weeks of the reseal being completed. We inspect the road again within the next two months and arrange a final sweep, if required, to maintain road safety and surface quality. After this, any additional sweeping will be completed as part of routine maintenance. 

When is road marking completed?

Road marking is reinstated after the first sweep of loose chip. We focus on legally required white and yellow road marking including traffic lanes and parking restrictions. 

Green road marking to provide improved visibility of cycle lanes is completed at least six weeks later once the road has cured enough for the specialised paint to stick to the surface.

We check the road markings again within 12 months and refresh any that have faded.

What can you do to help us?

Careful driving reduces loose chip and helps protect the finished seal. Drive to the posted speed limit, accelerate and brake gently, and avoid sharp turning movements. 

Share this page

Feedback

Has this page been helpful?
Thanks for your feedback.

Last updated 12 October 2026