This page contains information from the Territorial Authority. For information from the Requiring Authority, visit the central city reservoirs project webpage.

The Notice of Requirement (NOR) seeks to alter the existing designation A67 Water Reservoir (Ruakiwi Road) to enable the construction, operation, and maintenance of two reservoirs, a valve chamber, pipelines, and supporting infrastructure to supply water to the central city and the surrounding areas.

The NOR was publicly notified on 23 September 2025 and the submission period closed on 22 October 2025. Six submissions were received

Public notification of Notice of Requirement

In addition, Council is seeking feedback on a proposal to change the reserve classification for the proposed designated part of Lake Domain Reserve from a Recreation Reserve to a Local Purpose Reserve (Water Infrastructure) to better reflect its intended future use. This is a process under the Reserves Act 1977.

Public consultation also ran from 23 September - 22 October 2025. 

Hearings held 23 February 2026. Decision notified 20 March 2026.

Existing designation and Notice of Requirement boundary

Timeline

April 2025

Planning

22 August 2025

NOR Lodgement

23 September 2025

NOR Public Notification & call for submissions

22 October 2025

Submissions period closed

3 December 2025

s42A report 

19 December 2025

RA evidence 

23 January 2026

Submitter evidence

10 February 2026

Rebuttal

12 – 16 February 2026

Expert conferencing (if directed)

20 February 2026

Legal Submissions

Week of 23 February 2026

Hearings

20 March 2026

Decision Notified

Share this page

Feedback

Has this page been helpful?
Thanks for your feedback.