The below information relates to minor works in Hamilton city.
Peacockes Road from Peacockes Lane to Stubb Road |
Peacockes Roading Developments | 22 August 2022 to 22 December 2024 |
Horsham Downs Road from Moonlight Drive to 173 Horsham Downs Road |
Borman Extension Project | 10 January 2024 to March 2025 |
Borman Road from Barrington Drive to Horsham Downs Road |
Borman Road Urbanisation Works | 20 March 2023 to March 2025 24 hours a day 7 days a week |
Borman Road from Sirius Crescent to Kimbrae Drive Kimbrae Drive from Borman Road to Kimbolton Street |
Borman Road Extension Works | 28 February 2023 to November 2024 |
ANZAC Parade from Victoria Street to Grey Street Puutikitiki Street from ANZAC Parade to Beale Street Memorial Drive from ANZAC Parade to Riro Street |
Construction of apartments | 12 January 2024 to 2 February 2026 |
Onion Road from Koura Drive to Redoaks Close |
Subdivision Connections | August 2023 to 5 November 2024 |
Victoria Street from Awatere Avenue to Fairfield Bridge Heaphy Terrace from Grey Street to Fairfield Road Fairfield Road from Heaphy Terrace to River Road |
Fibre Installation | 26 July to 30 November 2024 |
Wairere Drive Bisely Road Intersection |
Traffic Signal Maintenance Loop Cutting |
14 November 2024 7pm to 5am |
Tristram Street from Ward Street to Mill Street |
Founders Theatre Demolition | 21 June to 22 December 2024 |
Buchanan Place entire legnth |
Kerb and Channel Renewal | 14 November to 15 November 2024 |
McKay Drive Entire Length |
Footpath Renewal | 29 October to 6 December 2024 |
Cullimore Street Entire Legnth |
Watermain Replacement | 23 August to 13 December 2024 |
Heaphy Terrace from Brooklyn Road to Boundary Road |
Watermain Replacement | 15 August to 28 November 2024 |
Rhode Street Entire Legnth |
Watermain Replacement | 31 October to 9 December 2024 |