The below information relates to minor works in Hamilton city.

Peacockes Road
from Waiora Terrace to Stubb Road
Peacockes Roading Developments 22 August 2022 to 31 August 2025
ANZAC Parade
from Victoria Street to Grey Street
Puutikitiki Street
from ANZAC Parade to Beale Street
Memorial Drive
from ANZAC Parade to Riro Street
Construction of apartments  12 January 2024 to 2 February 2026
Onion Road
from Koura Drive to Redoaks Close
Subdivision Connections August 2023 to 31 March 2025
Mill Street
Ulster Street
Intersection
Traffic Signal Maintenance
Pole Replacements and Cable Renewals
19 January to 30 January 2025
7pm to 6am
Knighton Road
from Greensboro Street to May Street
Footpath, Kerb and Channel Renewal 6 January to 17 January 2025
Clarkin Road
from Dalethorpe Avenue to McNicol Street
Footpath, Kerb and Channel Renewal 13 January to end of January 2025
Splitt Avenue
from Lewis Street to Landsdowne Crescent
Minor Surface Repairs 13 January to 17 January 2025
Keruru Street
from Weka Street to Makomako Street
Minor Surface Repairs 13 January to 17 January 2025
Hyde Avenue
from Blomfield Street to Millar Place
Minor Surface Repairs 13 January to 17 January 2025
Fifth Avenue
from Peachgrove Road to John Street
Minor Surface Repairs 13 January to 17 January 2025
Wentworth Drive
from Woodham Place to Innswood Place
Minor Footpath Repairs 13 January to 17 January 2025
Holly Place
Entire Length
Minor Footpath Repairs 13 January to 17 January 2025
Saxon Wood Drive
Entire Length
Minor Footpath Repairs 13 January to 17 January 2025
Guildford Place
Entire Length
Minor Footpath Repairs 13 January to 17 January 2025
Wychbury Court
Entire Length
Minor Footpath Repairs 13 January to 17 January 2025
Lansbury Court
Entire Length
Minor Footpath Repairs 13 January to 17 January 2025
Woodham Place
Entire Length
Minor Footpath Repairs 13 January to 17 January 2025
Whitford Place
Entire Length
Minor Footpath Repairs 13 January to 17 January 2025
Aurora Terrace
from Dorothy Place to Cul-De-Sac
Minor Footpath Repairs 13 January to 17 January 2025
Fox Street
from Cook Street to Wellington Street
Minor Footpath Repairs 13 January to 17 January 2025
Fenwick Crescent
Entire Length
Minor Footpath Repairs 13 January to 17 January 2025
Masters Avenue
from Aurora Terrace to Silverdale Road
Minor Footpath Repairs 13 January to 17 January 2025
Howell Avenue
from Cobham Drive to Geoffrey Place
Minor Footpath Repairs 13 January to 17 January 2025
Silverdale Road
from Morrinsville Road to Ashbury Avenue
Minor Footpath Repairs 13 January to 17 January 2025
Nevada Road
Entire Length
Minor Footpath Repairs 13 January to 17 January 2025
McGregor Place
Entire Length
Minor Footpath Repairs 13 January to 17 January 2025
Mullane Street
from Morrinsville Road to Cul-De-Sac
Minor Footpath Repairs 13 January to 17 January 2025
O'Donoghue Street
from Hillcrest Road to Aurora Terrace 
Minor Footpath Repairs 13 January to 17 January 2025
Hillcrest Road
from Edinburgh Road to O'Donoghue Street
Minor Footpath Repairs 13 January to 17 January 2025
Morris Road
from Beech Crescent to Morrinsville Road
Minor Footpath Repairs 13 January to 17 January 2025
Johnsview Terrace
Entire Length
Minor Footpath Repairs 13 January to 17 January 2025
McCracken Avenue
Entire Length
Minor Footpath Repairs 13 January to 17 January 2025
Hillcrest Road
Mansel Avenue
Intersection
Minor Kerb Renewal 13 January to 17 January 2025
Ohaupo Road
from Normandy Avenue to Urlich Avenue
Footpath Renewal 6 January to 3 February 2025
Lindsey Crescent
from Prior Place to Cul-De-Sac
Footpath Renewal 6 January to 3 February 2025
Hukanui Road
from Clarkin Road to Tongariro Street
Road Rehabilitation 6 January to 10 February 2025
Exelby Road
from Rotokauri Road to Burbush Road
Resealing One day in the week
13 January to 17 January 2025
Ennion Rise
from Horsham Downs Road to Waikato Expressway Overbridge
Resealing One day in the week
13 January to 17 January 2025
Gordonton Road
from Borman Road to Thomas Road
Resealing One day in the week
13 January to 17 January 2025
Cullimore Street
Entire Legnth
Watermain Replacement 23 August 2024 to 31 January 2025
Heaphy Terrace
from Brooklyn Road to Boundary Road
Watermain Replacement 15 August 2024 to 31 January 2025
Rhode Street
Entire Legnth
Watermain Replacement 31 October 2024 to 31 January 2025
Gilbass Avenue
Entire Length
Watermain Replacement 4 November 2024 to 17 January 2025