Work to replace the roof on Hamilton’s Central Library starts on 29 January.
The six-week project represents Hamilton City Council’s commitment to proactively maintaining the large public buildings it is responsible for on behalf of the city’s residents.
The Central Library is the flagship of the Hamilton City Libraries service, and Libraries Director Rebecca Whitehead says it also houses the largest percentage of the libraries’ collection, including heritage materials.
“The re-roofing project is what we term a ‘planned renewal’,” she says. “Like any building owner, the Council must look after its asset and this is a project we have budget allocated for.
“As we hold hundreds of thousands of loan items and city archives, it is vital our building is maintained to a high standard.”
Mrs Whitehead says customers will notice a fair bit of associated construction activity and noise around the Central Library as contractors undertake the work.
The re-roofing project will require the use of two cranes to lift new roofing material on to the top of the building. One crane will operate from outside the front of the Central Library, while the other will be used for one day from an adjacent carpark.
Mrs Whitehead says there will be no restrictions on access into and out of the Central Library for customers, although from time to time parts of the third floor will be off-limits from time to time.
“There will be some minor disruption for customers, but our staff will be able to assist people who require items from that level.”
There are no changes to the Central Library’s operating hours while the project is being undertaken.