Construction of a new roundabout to provide safer access to Ohaupo Rd/State Highway Three and a future link to the new Peacocke neighbourhood started again during Level 3 under specific health and safety controls for minimising COVID-19 risk.

In the next few days the southern end of Dixon Rd at the Ohaupo Rd intersection will close to through traffic for up to two months as part of the works. The closure was originally scheduled to start on March 25, just days before the lockdown rules were announced and implemented. Detour signage and electronic messaging will be in place on the approaches to the closure.

The project team is excited to be back at work and are implementing additional safety measures for site workers in line with government and health advice for workplaces.

This is the second and final time this part of Dixon Rd will be closed to through traffic for the construction of the roundabout.

The road needs to be closed to install a wastewater main, stormwater outlet and to construct the new pavement at the southern end of Dixon Rd to work in with the new roundabout layout.

Prior to lockdown more than 50,000m3 of earth had been moved and 10,000m3 of rock brought. The project will also benefit the environment, with around 17,000 new plants planned in and around the roundabout. Construction is expected to be complete by the end of the year.

Funding for the Peacocke programme is made up of a $180.3M 10-year interest-free loan and $110.1M of Waka Kotahi NZ Transport Agency subsidies.